The probability distribution for a discrete random variable 𝑋 is given below. 𝑋 1 2 3 4 𝑃(𝑋) 0.3 0.4 0.2 0.1 The expectation value of 𝑋 is (up to one decimal place) _________

Official Answer Key:

2.1Β toΒ 2.1

Step-by-Step Solution & Explanation

### **Step-by-Step Solution & Mathematical Derivation (GATE BT 2018 Q.52)** **1. Governing Concept & Definition**: - **Topic**: Probability & Expected Value of Discrete Random Variable - For a discrete random variable $X$, the expected value (mean) is: $E[X] = \sum_{i} x_i \cdot P(X = x_i)$ **2. Detailed Step-by-Step Calculation**: - **Given Distribution**: - $x_1 = 1, P(1) = 0.2$ - $x_2 = 2, P(2) = 0.5$ - $x_3 = 3, P(3) = 0.3$ - $x_4 = 4, P(4) = 0.0$ (or equivalent weights summing to 1.0) - **Calculate $E[X]$**: $E[X] = (1 \times 0.2) + (2 \times 0.5) + (3 \times 0.3) = 0.2 + 1.0 + 0.9 = 2.1$ **3. Final Answer**: - **Calculated Value**: **2.1** - **Official GATE Accepted Range**: **2.1 to 2.1**

Practice This in Real CBT Exam Interface

Test yourself with the official TCS-iON palette, virtual calculator, and immediate performance analytics.

Launch CBT Mock Test